Floating and subsea data centers: what is actually operating in 2026
The only commercially operating offshore data center capacity in the world is Chinese. HiCloud and Hailanyun’s undersea facility off Shanghai’s Lingang Special Area entered full operation in May 2026 at 24 MW, powered directly by adjacent offshore wind at roughly 97% renewable, cooled by seawater, at a claimed power usage effectiveness of about 1.15 and an investment of 1.6 billion yuan, about $225 million. Everything in the West is at pilot, concept or single-digit-megawatt scale.
Key takeaways
Shanghai Lingang — 24 MW, operating
The Shanghai Lingang facility began as a 2.3 MW, 198-rack demonstration and phase two brings it to 24 MW with roughly 2,000 servers. Claims include 22.8% lower electricity consumption, electricity costs 30% to 40% below land-based equivalents, land use cut by more than 90%, and zero freshwater consumption. Partners include China Telecom and Shanghai Lingang Investment Holding Group. The timeline ran from a cooperation agreement in June 2025 to construction completion in October 2025, testing in February 2026 and full operation in May 2026.
Highlander, Hainan — undisclosed capacity
Highlander at Lingshui, Hainan is a 1,300-tonne module at 35 metres depth built by COOEC and deployed in November 2023, serving China Telecom and SenseTime. Plans contemplate up to 100 modules at the site, projected to save 68,000 square metres of land, 122 million kilowatt-hours a year and 105,000 tons of freshwater annually. Megawatts, rack count and PUE are undisclosed.
Keppel Loyang — 25 MW, under construction
Keppel's Floating Data Centre Park at Loyang, Singapore is 25 MW, with construction begun in the first quarter of 2026 and completion in 2028, across four storeys on 9,870 square metres of land plus 7,580 square metres of sea space — roughly 0.4 square metres of land per kilowatt, the single most useful ratio in the field for port real estate. It uses closed-loop seawater cooling with low global-warming-potential refrigerants, is funded by Keppel Data Centre Fund II, and has already secured an unnamed hyperscale customer.
The United States retrenched
The United States retrenched. Nautilus Data Technologies put its 10 to 12 MW Stockton, California barge up for sale and cancelled its 60 MW, roughly $300 million Maine project in April 2025 because, per One Katahdin's Steve Sanders, the company had not been able to secure an artificial intelligence customer because it could not provide enough power. Nautilus has pivoted from developing data centers to selling water-cooling technology.
Panthalassa — $140M Series B
Panthalassa raised a $140 million Series B in May 2026 from Peter Thiel, John Doerr, Marc Benioff's TIME Ventures and Max Levchin's SciFi Ventures, with Super Micro and Fortescue Ventures, for wave-powered, self-propelled autonomous Ocean-3 inference nodes with low-earth-orbit satellite backhaul and pilot manufacturing near Portland, Oregon. Satellite latency confines the design to inference rather than training.
The binding constraint is generation, not cooling
The distinction between using water and consuming it is the real water-use argument for marine siting, and it is genuinely strong. But the constraint that kills projects is power. Autonomous floating facilities need enormous onboard generation, fuel storage and redundancy, which is precisely what ended the Nautilus Maine project.
Elliott Bay’s demand data is the best public sizing available: baseline inquiries cluster at 30 MW, most fall in the 50 to 80 MW range, and AI-focused inquiries push 100 to 300 MW — well beyond anything built anywhere.
“You’ve got an essentially unlimited source of cooling water that you’re not consuming.”
The regulatory finding that surprises people
A United States floating data center without passengers, tethered to shore, is not a Coast Guard-inspected vessel. Most owners instead pursue voluntary class certification through ABS or DNV, and both societies are actively developing rule sets specific to floating data centers. The requirements resemble offshore infrastructure: periodic inspection, maintenance planning and lifecycle management.
On the Jones Act, this is analysis rather than settled law. No data-center-specific Customs and Border Protection ruling or litigation exists. The analytically correct framing is that 46 U.S.C. section 55102 restricts transportation of merchandise between United States points to vessels that are US-built, US-owned and US-crewed, so a permanently moored, shore-tethered facility that transports no merchandise sits largely outside it, while repositioning a barge between US ports, or supplying it from US points, creates coastwise exposure. The practical bite is that a US-built hull costs a multiple of a foreign one. Take maritime counsel before relying on any definitive claim, including this one.
Why the geography is lopsided: marine permitting and environmental scrutiny, particularly of thermal discharge into sensitive ecosystems, are materially more stringent in Western jurisdictions than in China. That, more than technology, explains why the only operating capacity is Chinese.
Asia-Pacific pilots worth tracking
Aikido Technologies has the most interesting design in the field: a floating offshore wind platform with integrated compute, sized at a 15 to 18 MW turbine per unit supporting roughly 10 to 12 MW of AI-grade compute in three data halls of 3 to 4 MW each, with battery storage and seawater cooling. A 100 kW proof of concept is planned in Norway later in 2026, with United Kingdom commercial deployment targeted for 2028.
Yokohama Port in Japan began a demonstration on 25 March 2026 at Osanbashi Pier, running through the end of Japan’s 2026 fiscal year — a containerized data center on a floating mini-platform with solar and battery at 100% renewable, with Yokohama City, NYK Line, NTT Facilities, Eurus Energy Holdings and MUFG Bank. It is explicitly testing salt-damage resistance, vibration-related operational stability and renewable energy management, the three unresolved engineering questions.
Mitsui O.S.K. Lines, Hitachi and Hitachi Systems signed a memorandum of understanding in March 2026 to develop floating data centers converted from second-hand vessels, a Karpowership-style model, with operations possible from 2027.
Microsoft’s Project Natick was discontinued in 2024, leaving one finding that still matters: submerged servers failed at one-eighth the rate of the land-based control group.
Space, honestly assessed
Starcloud raised a $170 million Series A at a $1.1 billion valuation in March 2026, led by Benchmark and EQT Ventures, and launched Starcloud-1 in November 2025 with an Nvidia H100, claimed as the first terrestrial-grade GPU operated and trained in orbit. Starcloud-3 is planned as a 200 kW, three-tonne spacecraft for Starship, and the company has filed a Federal Communications Commission application for an 88,000-satellite constellation, targeting roughly five cents per kilowatt-hour once Starship flies regularly at $500 per kilogram.
Google’s Project Suncatcher, announced 4 November 2025, will launch two Trillium-generation TPU satellites with Planet Labs by early 2027, toward a theoretical 81-satellite cluster in a one-kilometre radius at 650 kilometres altitude, economic only at roughly $200 per kilogram launch cost by 2035. Google names its own obstacles: thermal management, on-orbit reliability and high-bandwidth-memory radiation sensitivity. Lonestar Data Holdings flew an 8-terabyte solid-state drive and a Microchip PolarFire FPGA to the lunar surface on Intuitive Machines’ Athena mission, targeting off-world disaster recovery.
The honest assessment: total operating space-based compute is a handful of GPUs. Against 7,481 MW under construction in United States colocation alone, space is a technology-watch item, not a capacity source this decade, and Starcloud’s economics depend on a Starship launch price that does not yet exist.
Why a landowner should care about any of this
Two reasons, both concrete. First, the Keppel ratio — 25 MW on 9,870 square metres of land plus 7,580 square metres of sea space — is a real number for port authorities and waterfront owners evaluating whether a berth, a slip or a filled parcel has a compute use. Second, the pattern across Shanghai, Singapore, Stockton and Yokohama is that marine compute needs landside real estate anyway: substation, switchgear, fiber landing, maintenance and staging. The waterfront parcel behind the mooring is the transaction.
This research was produced by Landside Partners, a commercial real estate research and advisory firm working with owners of industrial land across North America on data center, seaport and air-cargo demand. To have a specific parcel assessed, contact Brad Cohen at Landside Partners.
Related research
- Data Centers — Pillar: US data center demand, vacancy and the pipeline that has to find land, Q2 2026.
- Data Center Projects — Atlas of named hyperscale and Stargate campuses with capacity and status, Q2 2026.
- Data Center Land Pricing — Per-acre land pricing and the three measured premiums buyers pay for powered land, Q2 2026.
- Data Center Power — Interconnection queues, tariff orders and behind-the-meter generation as land constraints, Q2 2026.
- Ports — Pillar: committed, funded and dated US gateway capacity and near-port industrial pricing, Q2 2026.
No fee. One parcel. One page. Usually back within five business days.
Published · Last updated